Project timelines are correct at the time of publication and may be subject to change without notice.
| Activity |
Timing
|
| Commence early and enabling works |
August 2009 |
| Commence Request for Proposal for the Operator Franchise |
June 2010 |
| Construct Gold Coast University Hospital Station shell at Parklands Drive |
July 2010 - 2011 |
| Roadworks north and south |
Late 2010 - late 2011 |
| Appoint Operator Franchise |
March 2011 |
| Commence works — Operator Franchise |
Late 2011 |
| Commence service — Stage One of rapid transit system |
2014 |